WORK DONE WITHOUT PERMITS
Ø COMPLETED PERMIT APPLICATION TO INCLUDE:
o CONSTRUCTION PERMIT FORM
TECHNICAL
SECTIONS AS APPLICABLE
o BUILDING TECHNICAL SECTION
o FIRE PROTECTION TECHNICAL SECTION
o ELECTRICAL TECHNICAL SECTION
o PLUMBING TECHNICAL SECTION
o 2 SETS OF PLANS
o
3 COPIES OF PROPERTY SURVEY IF APPLICABLE and include payment for Zoning Permit Fees of
$50.00 payable to “
Ø
ANY FOOTINGS MUST BE EXPOSED AS DIRECTED OR
CERTIFIED IN WRITING BY A NJ LICENSED STRUCTURAL ENGINEER.
Ø
ELECTRICAL INSTALLATIONS MUST BE CERTIFIED BY A
NJ LICENSED ELECTRICAL CONTRACTOR OR EXPOSED FOR ROUGH WIRNG INSPECTION. (THE
CERTIFICATION MUST BE SIGNED AND SEALED AND ON THE ELECTRICAL CONTRACTORS
OFFICIAL LETTER HEAD.)
Ø
PLUMBING INSTALLATIONS MUST BE CERTIFIED BY A NJ
LICENSED PLUMBING CONTRACTOR OR EXPOSED FOR ROUGH INSPECTION. A SMOKE TEST MAY
BE REQUIRED PRIOR TO FINAL APPROVAL.
(THE CERTIFICATION MUST BE SIGNED AND SEALED AND ON THE PLUMBING CONTRACTORS OFFICIAL LETTER HEAD.)
Ø A PENALTY OF $2000.00 WILL BE ASSESED AND ADDED TO THE PERMIT FEE AFTER REVIEW.
Ø
EFFECTIVE
Jan 4, 2010 there will be a Zoning Permit Fee of $50.00 payable to “